Virginia SCC orders data centers to pay for transmission infrastructure
Headline from WFXR Roanoke
(WFXR)- The Virginia State Corporation Commission (SCC) ordered Dominion Energy to develop a new tariff requiring data centers to cover most of the costs associated with new high-voltage transmission infrastructure. According to the order, the original filing by Dominion Energy, for more than $1.
WFXR Roanoke's own description from its feed. We collect headlines and these descriptions, not full articles; read the original reporting below.
More of the cost to build the high-voltage transmission lines that serve as power highways across the state could soon be covered by data centers, after a recent decision by state regulators. The State Corporation Commission has ordered Dominion Energy to develop a policy to directly assign the cost…
(The Center Square) – Dominion Energy must return to Virginia regulators this fall with proposed changes that could shift more transmission infrastructure costs to data centers and other large electricity users under a new order from the State Corporation Commission.
(WFXR)- The Virginia State Corporation Commission (SCC) ordered Dominion Energy to develop a new tariff requiring data centers to cover most of the costs associated with new high-voltage transmission infrastructure. According to the order, the original filing by Dominion Energy, for more than $1.
The State Corporation Commission (SCC) ordered data centers to cover the cost of transmission infrastructure built exclusively for those facilities, according to a Wednesday afternoon release from Gov. Spanberger.
Identical headlines usually mean shared wire copy. They are counted as separate articles but are not independent confirmation.
Virginia SCC orders data centers to pay for transmission infrastructure | Since Then