Coverage dated September 17, 2026 to September 18, 2026

Orange Barrel Report September 18

Headline from KBSI Cape Girardeau

TENNESSEE, (KBSI) —The Hamilton Place Boulevard Interchange project is now 75% complete! Since construction began, crews have made major progress on three new bridges, including setting beams, constructing bridge decks and pouring concrete for the on/off ramps.

KBSI Cape Girardeau's own description from its feed. We collect headlines and these descriptions, not full articles; read the original reporting below.

Reports & sources

2 articles, oldest first.

  1. KBSI Cape Girardeau

    Orange Barrel Report September 17 (opens KBSI Cape Girardeau)

    Published

    KBSI Cape Girardeau's feed description

    TENNESSEE, (KBSI) —The Hamilton Place Boulevard Interchange project is now 75% complete! Since construction began, crews have made major progress on three new bridges, including setting beams, constructing bridge decks and pouring concrete for the on/off ramps.

  2. KBSI Cape Girardeau

    Orange Barrel Report September 18 (opens KBSI Cape Girardeau)

    Published

    KBSI Cape Girardeau's feed description

    TENNESSEE, (KBSI) —The Hamilton Place Boulevard Interchange project is now 75% complete! Since construction began, crews have made major progress on three new bridges, including setting beams, constructing bridge decks and pouring concrete for the on/off ramps.

Orange Barrel Report September 18 | Since Then