Coverage dated July 16, 2024 to July 17, 2024

NASA cancels moon rover mission with lander from Pittsburgh-based Astrobotic

Headline from CBS News, from the development of Jul 17, 2024

Newest development Jul 18, 2024 · 4 reportsNASA nixes moon rover mission due to skyrocketing costs, launch delays

NASA is canceling a water-seeking moon rover because of cost overruns and launch delays.

CBS News's own description from its feed. We collect headlines and these descriptions, not full articles; read the original reporting below.

Developments in this update

2 dated developments, oldest first, newest marked. Each is named by one outlet's own headline; open its reports to see every outlet that covered it.

  1. Names this update

    NASA cancels moon rover mission with lander from Pittsburgh-based Astrobotic

    Headline from CBS News ·

  2. Newest

    NASA nixes moon rover mission due to skyrocketing costs, launch delays

    Headline from Fox News ·

Reports & sources

11 articles, oldest first.

  1. The Republic

    NASA cancels its moon rover mission, citing cost overruns and launch delays (opens The Republic)

    Published

    The Republic's feed description

    WASHINGTON (AP) — NASA said Wednesday it’s canceling its water-seeking moon rover, citing cost overruns and launch delays. The Viper rover was supposed to launch in late 2023 aboard a lander provided by Astrobotic Technology, but extra testing and increased costs kept delaying the mission, threateni…

  2. Triblive

    NASA cancels Pittsburgh company's moon rover mission, citing cost overruns and launch delays (opens Triblive)

    Published

    Triblive's feed description

    WASHINGTON — NASA said Wednesday it’s canceling its water-seeking moon rover, citing cost overruns and launch delays. The Viper rover was supposed to launch in late 2023 aboard a lander provided by Astrobotic Technology, but extra testing and increased costs kept delaying the mission, threatening ot…

  3. Gizmodo

    NASA Cancels VIPER’s Trip to the Moon After Spending $450 Million on Rover (opens Gizmodo)

    Published

    Gizmodo's feed description

    Cost overruns and delays doomed the ice-hunting lunar rover.

  4. Universe Today

    NASA Stops Work on VIPER Moon Rover, Citing Cost and Schedule Issues (opens Universe Today)

    Published

    Universe Today's feed description

    NASA says it intends to discontinue development of its VIPER moon rover, due to cost increases and schedule delays — but the agency is also pointing to other opportunities for robotic exploration of the lunar south polar region.

  5. Fox News

    NASA nixes moon rover mission due to skyrocketing costs, launch delays (opens Fox News)

    Published

    Fox News's feed description

    NASA announced it is canceling its Viper moon rover project due to high cost and launch delays, but it plans to study the presence of lunar ice through other projects.

  6. CBS News

    NASA cancels moon rover mission with lander from Pittsburgh-based Astrobotic (opens CBS News)

    Published

    CBS News's feed description

    NASA is canceling a water-seeking moon rover because of cost overruns and launch delays.

  7. New York Times

    NASA Spent $450 Million on a Moon Rover. Now It’s Canceling the Mission. (opens New York Times)

    Published

    New York Times's feed description

    Delays and concerns about NASA’s future budgets doomed the VIPER mission, which aimed to search for ice near the moon’s south pole.